| |
School Board
authorizes February 28 vote to address long-range facilities
utilization and improvement plan
December 7, 2005
A Message from Dr. Don Helmstetter, Superintendent
Greetings!
Last night, on Tuesday, December 6, the Spring Lake Park District 16
School Board authorized a bond referendum of $95.9 million for a
major facilities improvement plan to repair, renovate, and construct
school district facilities. The referendum will be held on Tuesday,
February 28, 2006, approximately three months from now. If the
project is approved by voters, it will cost the average homeowner in
District 16 about 50 cents a day.
The Board’s decision was not unexpected; in fact, it has been long
awaited. The project began in March 2004, when the District
contracted with engineers and architects to inspect and assess its
schools and facilities.
The study gained momentum – and considerably more community exposure
-- once a Community-School Task Force began meeting in February
2005. The Task Force completed its assignment in November. The
Board’s action on December 6 reflects completely the recommendations
of this Task Force, but the Board also included in their plans
additional construction at Woodcrest Elementary School that was
previously discussed, but not an a viable option at the time of the
Task Force study.
The Board decision to authorize a bond election goes hand-in-hand
with anticipated approval by the MN State Department of Education
for the project. In addition to achieving our many objectives for
the future, our project is expected to comply with state guidelines
that address and correct critical issues.
A successful bond referendum is the foundation of the School
District’s long-range facilities utilization and improvement plan to
meet all of today’s standards while anticipating needs well into the
future.
The bond referendum would also enable the District to handle
significant present and anticipated population student growth, as
well as to complete the maintenance needs left over from the bond
issue ten years ago. The bond funds will repair and modernize these
old structures (buildings aged between 34 and 50 years old),
including replacing and repairing old single-pane windows, original
boilers, and worn out roofs.
From fall 2004 to fall 2005 alone, we experienced an enrollment
growth of 200 students. The very real housing boom in Blaine, which
will bring us over 800 new students, makes our district among the
few that are actually experiencing a growth in student population,
but it also requires additional classroom space. Funds will not only
build a new elementary school in the fastest growing area of our
school district, but will also create additional classrooms at the
middle and elementary schools. Facilities--including gyms,
cafeterias, athletic and fine arts areas--will be updated to serve
an almost 20% increase in the student population.
The “high school complex,” which houses not only Spring Lake Park
High School, but also Kenneth Hall Elementary, our Early Childhood
Programs, Community Services, Learning Alternatives Programs, and
the District Office, is woefully undersized and no longer meets
today’s state guidelines.
According to John Ryberg, Facilities Specialist for the Minnesota
Department of Education, there is too much activity on this site
and, in order to meet even minimum standards and receive state
approval of our facilities plan, the district must close Kenneth
Hall Elementary School. However, the State Department will allow us
to retain some of the school’s useable space — such as the cafeteria
and gymnasium--for student and community use.
The district will also take down the 50 year-old sections of the
high school and build a new, two-story section for classrooms, as
well as consolidate and expand the physical education and fine arts
areas. Some of the space gained will assist in providing more
much-needed outdoor teaching stations for physical education, and it
will also improve student safety and security at our school
entrances and a safer traffic flow for buses and vehicles. In this
plan, the new main entrance for the high school would be located on
the east side of the school.
In a preliminary update to the School Board this past summer, a Task
Force member commended the school district and its custodians for
the tremendous effort in keeping the schools clean and running
efficiently. However, he also reminded the district that many of the
buildings have “already outlived their original intended life span.”
Another Task Force member stated that now is the time for the
district to complete the task it started ten years ago with its 1995
bond referendum and to prepare these facilities for the next
generation of students.
The facilities study and its progress have been discussed in more
than 50 public meetings within the last two years, and, now that the
Board has authorized a bond referendum election, there will be more
public meetings after the first of the year.
I encourage you to follow the progress of this discussion in the
continual updates on the web site, stories in local newspapers, in
upcoming district publications, and on cable television. Our web
site has sections available to have your questions answered, to
schedule a “coffee party” information session, or to sign up for
facilities tours which will be scheduled after the first of the
year. A series of community meetings will be announced in
mid-December and scheduled throughout the month of January.
Dick Morin, a Fridley resident, parent of District 16 graduates, and
a member of the Task Force, probably described our facilities needs
the best with a comment at one of our community information
meetings. He said that “it just gets more expensive the longer we
wait. We need to step up to the challenge and do it right. These are
our schools, our children, our responsibility.”
|